Test Rigs for Aerospace Validation: Planning an Aerospace Electronics Test Rig

by | Last updated Nov 16, 2026

An aerospace electronics test rig is the set of fixtures, power sources, stimulus equipment, instrumentation and monitoring that holds a unit in a defined configuration and records its performance during testing. If the rig does not represent relevant aspects of the installed equipment, the results may not show how the unit will behave on the aircraft. A problem found during a formal campaign may mean fixture rework, repeat testing or another laboratory booking.

This post follows our Aerospace IMU Selection post which covered how to compare sensors and what to ask suppliers. Here, the focus is on how rigs are designed and what they need to show, with technical guidance for engineers and procurement questions for programme managers. Environmental standards such as DO-160 are cited only where a rig detail depends on them; DO-160 Electronics Testing for Engineers: Scoping Environmental Qualification covers the standard itself.

Which aerospace electronics test rig a programme may need (environmental, functional and system-level)

Programmes use the word rig for several different set-ups, each supporting a different kind of evidence. Three groups cover the main planning decisions:

  1. Environmental qualification rigs: Shakers with fixtures, climatic and altitude chambers, centrifuges or static-load arrangements, and programmable power sources expose the unit to defined conditions. They support environmental qualification evidence, and their value depends on how closely the mounting and electrical connections match the installation.
  2. Functional and performance monitoring rigs: Stimulus, loads, bus monitors, and data logging show whether the unit meets its performance criteria before, during and after exposure. The criteria come from the equipment specification rather than from the rig.
  3. System integration rigs: Hardware-in-the-loop benches and iron bird rigs connect real hardware to simulated surroundings. Gantner Instruments describes a system integration test rig as a mock-up used to develop and validate system and software function with pre-production or production components, and an Aerospace Testing International feature on iron bird rigs reports that programmes can begin with simulated models and substitute hardware as it becomes available.

The sections below follow that order: environmental rigs, where fixture and mounting choices can affect the result; electrical and monitoring set-ups; and the laboratory and records needed to make the evidence usable.

Fixtures and mounting (what the unit actually experiences on the shaker)

On a shaker, the fixture sits between the armature and the unit, and it can change the response measured at the test article. Vibration Research’s fixture design guidance notes that a fixture resonance within the control bandwidth can make the controller try to drive through it, potentially causing control instability, excessive drive levels or damage to the shaker system. The guidance recommends keeping fixture natural frequencies well above the test band, but the required separation should be assessed against the test procedure, fixture response and control strategy rather than treated as a universal rule.

Fixtures should be designed and verified rather than assumed to behave as intended. A 2021 study of a fixture for an avionics flight control panel targeted a fixture natural frequency above the top of its 5 to 500 Hz test range; its finite element predictions differed from measured natural frequencies by between 9.7% and 14.6%, depending on axis. Analysis can inform the design, while measurement helps establish how the completed fixture behaves.

Control accelerometer placement matters as well. Siemens Simcenter explains that a control accelerometer at a peak in a mode shape can lead to under-testing elsewhere, while one at a node may cause the controller to increase drive levels unnecessarily and risk over-testing. HBK recommends using several accelerometer positions rather than relying on a single one. The appropriate locations depend on the fixture, test article, mode shapes and control method, so they should be selected for the specific set-up.

The mounting should also reflect the installation where that is relevant to the test objective. If the aircraft installation uses a bracket, isolators, a connector backshell and a clamped harness, a rig that replaces them with a rigid plate and a short cable tests a different configuration. Aerospace Vibration Electronics: Designing for Vibration and Shock Qualification covers how those elements can shape the response.

🛠️ DESIGN CONSIDERATION

Check the fixture response on the shaker before testing, including any fixture-only survey used to identify rocking or fixture modes. A fixture-only survey does not establish the response of the complete assembly: where the test plan calls for it, assess the fixture with representative mass, mounting and centre of gravity, or with the test article under an appropriate reduced-level procedure. Give each fixture a control number and retain its drawing and survey results in the test record.

 

Large units and crash safety (static-load rigs and centrifuges)

Sustained crash safety testing applies an inertial load to a representatively mounted unit. Element’s DO-160 guidance describes a centrifuge or sledge as the normal approach under DO-160G; in certain cases, a static load applied through the centre of gravity may be acceptable. Whether that alternative is suitable depends on the applicable procedure and test conditions. If the unit cannot be mounted safely in the required orientation, or the load cannot be applied appropriately, a purpose-built rig may be needed.

Where a unit has to be powered or monitored during constant-acceleration testing, DES describes wiring from terminals on the centrifuge arm to slip rings on the drive shaft, carrying power and data to stationary equipment outside the centrifuge. Shock fixtures have separate requirements. A planning article from Aerospace Testing International says the Section 7 fixture should be resonant-free and easy to remove from the table when changing axes, and describes crash safety shock as a potentially damaging test that is run separately. Confirm the required sequence and method against the applicable DO-160 section, category and agreed test procedure rather than relying on a general planning article.

⚠️ CRITICAL ALERT

Establish at the start of the programme whether crash safety testing applies and which method is permitted by the applicable procedure. Confirm that the representatively mounted unit will fit the intended centrifuge or sled, or that a static-load arrangement is acceptable for the case. Agree the method in the test plan with the customer or certification contact. A load rig designed late may have to accommodate a unit already designed around a different mounting.

 

Power and climatic set-ups (reproducing the aircraft electrical and thermal environment)

Programmable AC and DC power sources stand in for the aircraft electrical system. Electronic Design reports that a programmable source can store standard test requirements for later recall, and that setting up such systems brings difficulties in obtaining repeatable results, documenting the test setup and validating setups to the required criteria. Interference Technology notes that power input tests can be performed in the EMC laboratory by EMC test personnel, so the laboratory that holds the shaker may not be the one that holds the power and EMC equipment.

Climatic rigs bring their own constraints. The Aerospace Testing International planning article notes that the performance test defined in the procedure must be achievable within the time allowed by the temperature profile. The monitoring rig should therefore be planned around the required checks and available test time. Where temperature and vibration are combined, Electronic Design adds that fixture design must consider heat flow, insulation of the unit from the fixture and armature mass, and condensation control.

Aerospace test rig performance monitoring and pass criteria 

A unit that survives a test but is not monitored during exposure may still have pre- and post-test results, but those results alone may not show whether it continued to meet its performance criteria throughout the exposure. The monitoring rig can capture parameters named in the equipment specification, such as outputs, bus traffic, supply current and built-in test status, with time stamps aligned to the test profile where needed. Where practical, an independent measurement path can help identify a fault in the monitoring chain. Pass criteria and any acceptable interruptions should be defined in the test procedure before the campaign starts.

Choosing a laboratory and keeping the rig traceable (accreditation, calibration and configuration)

A laboratory’s accreditation covers specific methods and scope. The A2LA scope of accreditation for NIAR’s environmental test laboratory lists DO-160 sections by revision and notes that the scope includes withdrawn or superseded methods. Compare the current scope against the sections and revision named in the test plan rather than relying on a general statement of accreditation. Check the scope directly before booking, as the published listing may change.

Measurement credibility depends on suitable, traceable calibration. IEEE’s overview of test facilities describes a hierarchy from primary standards through transfer standards to working instruments, with documented uncertainty at each step. The rig’s instrumentation, including control and monitoring accelerometers, power measurement equipment and chamber sensors, should have calibration records that are valid for the test dates and appropriate to the measurement range and required accuracy.

Revision status can change which method applies. RTCA’s published information has listed DO-160G as the current published revision, while its 2025 year in review reported that DO-160H publication was expected in autumn 2026. As this status can change, check RTCA’s DO-160 page immediately before publication and confirm in the test plan which revision applies to the programme. Publication of a new revision does not, by itself, establish which revision applies to every project.

Record the test article configuration, fixture identity, instrumentation, controller software versions and procedure revision. These records help establish which set-up produced the results and support later review or repeat testing.

Case Study: Ariane 501 and the Rig That Used Simulated Inertial Outputs

On 4 June 1996, the maiden flight of Ariane 5 ended in failure about 40 seconds after initiation of the flight sequence, according to ESA’s summary of the Inquiry Board report. The Board concluded that the failure followed a complete loss of guidance and attitude information, caused by specification and design errors in the inertial reference system software. It also concluded that development reviews and tests had not included adequate analysis and testing of the inertial reference system or the complete flight control system.

The test arrangements are the relevant part. ESA’s summary states that the alignment function of the inertial reference system was not taken into account in the simulations and that the equipment and system tests were not sufficiently representative. A published summary of the Board’s findings adds that the specification and equipment-level tests did not include Ariane 5 trajectory data, so the realignment function was not tested under simulated Ariane 5 flight conditions. It also records that using the simulated output of the system, rather than including almost the entire inertial reference system in the overall system simulations, was a choice made despite the latter being technically feasible.

ESA’s corrective measures included making the qualification test environment more representative, using real equipment and components systematically wherever possible, simulating real trajectories on the inertial reference electronics, and introducing overlap between successive tests at equipment, stage and system level.

Ariane 501 was a launch vehicle failure traced to software, not an environmental qualification failure. Its relevance here is the representativeness of the test set-up: simulated inertial outputs and simulations that omitted relevant operating conditions did not expose a fault that depended on the real system’s behaviour. This does not mean every rig must use real hardware. It means the test strategy should establish which behaviours, interfaces and operating conditions need to be exercised, and whether the chosen simulation represents them adequately. The same question applies to a shaker fixture, a power-source profile or a hardware-in-the-loop bench: does it present the unit with the conditions relevant to its intended installation and use?

Aerospace Electronics Test Rig Planning Risks

Rig problems can surface after a formal campaign has been booked: a fixture resonance within the test band, a unit too large for the planned centrifuge, a monitor that cannot complete its checks in the available time, or an accreditation scope that omits the revision in the test plan. Each may require fixture rework, procedure changes, repeat testing or a new laboratory slot. The cost depends on how much of the campaign must be repeated. Unit count is also a planning decision: the Aerospace Testing International planning article notes that, where enough units are available and a cost analysis supports it, each section can be run on a separate unit.

Fixture and mounting design

Vibration and shock results that reflect the installation

Resonance in the test band, or a mounting that differs from the aircraft, leading to rework or repeat testing

Control and monitoring instrumentation

A record of unit performance during exposure

Gaps in the record, or checks that cannot be completed in the time the profile allows

Large-unit load arrangement

Crash safety results for the representative mounting

A unit that does not fit the planned centrifuge, or a load rig that has to be designed late

Power and EMC set-up

Behaviour under the specified power conditions

Set-ups that cannot be repeated or documented consistently

Laboratory scope and calibration

Confidence in the measurements and the applicable method

Evidence questioned because the scope or calibration records do not match the test plan

System-level rig

Behaviour of real hardware with realistic surroundings

Faults that depend on both hardware and operating conditions found late

 

The table is a planning aid. The rigs a programme needs depend on the equipment, certification basis and agreed test plan. Define rig requirements during design and before booking the laboratory so that fixture, instrumentation and capacity constraints can be addressed before the formal test campaign.

Questions to ask a design or test partner (before you commit)

Programme managers and buyers can assess rig readiness by asking five questions:

  1. Rig scope and representativeness: Which rigs will be used for qualification, functional monitoring and system-level checks, and which parts of the installation (brackets, isolators, connectors, harness, real equipment) will they include?
  2. Fixtures and instrumentation: How are fixtures designed and verified, where will control accelerometers be placed, and how will the test record show the fixture’s own response?
  3. Large units and special loads: If the equipment is large, or needs a crash safety method other than a centrifuge, what arrangement is planned, and has it been agreed in the test plan?
  4. Laboratory and calibration: Does the laboratory’s accreditation scope cover the sections and revision in the plan, and what calibration records will accompany the report?
  5. Ownership and records: Who owns the fixtures, rig software and test data, and what configuration records will be handed over for later campaigns or design changes?

Planning the aerospace test rig before qualification

An aerospace electronics test rig defines the conditions under which test results are produced. Fixture design, mounting, power and monitoring set-ups, large-unit arrangements, laboratory scope and calibration records all affect how well the evidence supports the intended qualification claim. Planning these elements alongside the design can reduce the risk of fixture rework, repeat testing and results being challenged.

The Ariane 501 inquiry shows how tests that replace real equipment with simulated outputs, or omit relevant operating conditions, can fail to expose a fault. A design or test partner should be able to explain what the rig includes, how the set-up was verified and which records will be handed over. The next post in this series, Aerospace Design Assurance Documentation: Planning the Evidence for Airborne Electronics, looks at the plans, traceability and records that make up the wider evidence package.

WORK WITH IGNITEC

Ignitec’s engineers support airborne electronics programmes from early design through to qualification planning. If you are planning test rigs and fixtures, we can review your mounting, monitoring and laboratory approach, and identify rig risks before you commit to a test plan. 

Contact the team to discuss your programme and test rig strategy.

Planning test rigs and fixtures for airborne electronics qualification?
Ignitec’s engineering team supports airborne electronics development from initial architecture through environmental qualification. We help define fixtures, power and monitoring set-ups and laboratory arrangements so your test evidence reflects the installed equipment before you commit to a laboratory or a test plan. Contact our team to review your test rig strategy.

Key Points

  1. An aerospace electronics test rig combines fixtures, power and stimulus sources, instrumentation and monitoring equipment. It holds the unit in a defined, representative configuration and records how the unit performs during testing.
  2. Environmental rigs, functional monitoring rigs and system integration rigs support different kinds of evidence. A programme may need more than one, with each rig planned around the evidence it must produce.
  3. Fixture resonance, control accelerometer placement and the relationship between test mounting and aircraft installation can affect the response measured during testing. Fixtures should be designed, checked using a method appropriate to the test and documented.
  4. Large units may need a static-load arrangement or a purpose-built rig. Laboratory accreditation scope, suitable calibration records and configuration records also affect how the test evidence can be assessed.
  5. The Ariane 501 inquiry shows how tests that do not adequately represent the real equipment and operating conditions can miss a fault. Before committing, buyers should ask what the rig includes, how it was verified, who owns it and what records will be handed over.
What is an aerospace electronics test rig?

It is the combination of fixtures, power sources, stimulus equipment, instrumentation and monitoring used to hold a unit in a defined configuration and measure how it performs during testing. Environmental, functional and system-level rigs support different kinds of evidence.

What is the difference between a test rig and a test fixture?

A fixture is the mechanical interface that mounts the unit, for example on a shaker. A rig is the wider set-up, which can include the fixture, power sources, monitoring equipment and data capture.

Why does fixture resonance matter in vibration testing?

A resonance in the fixture within the test band can alter the vibration response at the test article and may contribute to control instability or excessive drive levels. Fixture modes should be assessed for the specific test set-up, and the fixture response checked by a suitable measurement method.

How can large equipment be tested for sustained crash safety?

Element’s guidance describes a centrifuge as the normal approach under DO-160G. In certain cases, a static load applied through the centre of gravity may be acceptable, depending on the applicable procedure and test conditions. Agree the method in the test plan with the customer or certification contact.

What should I check when choosing a test laboratory?

Check that the accreditation scope covers the test methods and revision named in the test plan, that calibration records cover the instrumentation, that the laboratory holds the equipment for every section in the plan, and what the report will record about the fixture and the unit configuration.